Smoke control design is the engineering of fans, dampers, doors, detection and controls so that smoke stays out of exit stairs and is kept above occupants in large spaces long enough for everyone to leave. It is not a product you add at the end. It touches HVAC, fire protection, electrical power and the permit file at once, which is why it goes smoothly when one team coordinates all of those disciplines from schematic design. At Bazini Engineering, mechanical, plumbing and fire protection are all in-house, and our senior engineers are the people you actually talk to.
TL;DR
- Smoke control falls into two families under NFPA 92: containment (pressurizing stairs, elevators, vestibules, zones) and management (exhausting or venting large volumes such as atriums).
- Under the International Building Code (IBC) Section 909, a mechanical system needs a rational analysis, an automatic sequence of operation and a UL 864 listed control unit.
- Stair pressurization is typically judged by a pressure window of 0.10 to 0.35 inches of water column with every door closed, and by door opening force at every floor.
- Testing is a special inspection, and the records must live at the building for its life.
- Settle the system type, the pressure targets and the controls ownership before drawings go to the authority having jurisdiction (AHJ).
Table of Contents
- What a smoke control system actually does
- Who needs to be at the table
- How to design a smoke control system, step by step
- Atrium smoke control
- Smoke control testing and what passes
- Why owners and architects bring this to one engineering team
- Where Bazini Engineering fits
- Our perspective
- FAQ
- Sources
What a smoke control system actually does
According to NFPA's technical staff, a smoke control system manages the movement of smoke and air to keep conditions tenable long enough for occupants to get out. In most high-rise buildings the design goal is life safety, with limiting spread beyond the floor of origin a secondary benefit.
NFPA 92, the Standard for Smoke Control Systems, sorts the methods into two groups:
- Smoke containment. Fans create a pressure difference across a barrier so smoke does not migrate through it. Typical applications are stairwell pressurization, elevator pressurization, vestibule pressurization, smoke refuge areas and zoned smoke control, where floors around the fire floor are pressurized.
- Smoke management. In a large-volume space and the spaces connected to it, the goal is to hold the smoke layer above the highest occupiable level or slow its descent. Tools are mechanical smoke exhaust and natural or gravity venting.
Both are started automatically by detection, such as sprinkler waterflow, smoke detectors or heat detectors. Passive features, fire-rated walls, smoke barriers and doors, do the other half of the work. A pressurization system with a leaky enclosure will not hold its numbers, so the architecture and the mechanical design have to be settled together.
Who needs to be at the table
The reader of this page usually has one slice of the job: the owner who must get a certificate of occupancy, the architect laying out stairs and atriums, the installer who will hang the fans and ducts, or the plumber and sprinkler trades whose waterflow devices start the sequence. Smoke control crosses all of them.
- Owners and managers carry the responsibility for retaining qualified people to design and test the system. One municipal bulletin, San Antonio's Information Bulletin 185, says so explicitly, and it also recommends meeting the plan reviewer at preliminary design to agree on goals and performance criteria.
- Architects control the things that decide whether pressurization works: stair enclosure construction, door hardware, vestibule layout, shaft locations and atrium geometry.
- HVAC and boiler installers need to know that fans, dampers and ductwork serving smoke control have different rules than comfort systems. Fire and smoke dampers, for instance, are not permitted in some jurisdictions' pressurization ductwork, while backdraft dampers are allowed within the sequence of operation (Fairfax County, Virginia, fire marshal guidelines).
- Plumbers and sprinkler trades supply the waterflow signals that often trigger the sequence and must coordinate zones with the fire alarm.
Because one answer can change another trade's scope, an engineering team that already holds mechanical, plumbing and fire protection design under one roof removes a lot of hand-offs. That is the case for keeping this work together rather than splitting it across consultants.
How to design a smoke control system, step by step
The IBC and NFPA 92 give the framework. Local jurisdictions add their own requirements, so treat the figures below as the model-code baseline and confirm them with your AHJ.
1. Establish whether smoke control is required and why
Triggers include high-rise buildings, atriums, underground buildings and smoke-protected assembly seating. A common one is the smokeproof enclosure requirement for interior exit stairs serving floors more than 75 feet above the lowest level of fire department vehicle access. Pressurizing the stair is the typical way to satisfy it. Fairfax County's guidelines under the Virginia Construction Code spell this out, and it mirrors the IBC logic.
Where it goes wrong: assuming the trigger is the same everywhere. New York City runs its own code and agency procedures, so a project there should be reviewed against the NYC Building Code and the Department of Buildings and FDNY process, not against a model-code summary. Our NYC permit filing work covers that coordination with those agencies.
2. Pick the approach and set the design criteria
Before mechanical design begins, the constraints and design criteria must be set. NIST's Design Manual for Smoke Control Systems says as much. Decide:
- Passive or mechanical.
- Technique: pressurization, exhaust or airflow.
- Design fire, including sprinklers and likely fuel.
- Duration of operation.
IBC Section 909.4 expects the design to rest on a rational analysis by a registered design professional, accounting for stack effect, fire-induced temperature changes, wind, climate and how long the system must run, per the Society of Fire Protection Engineers' 2025 FPEeXTRA summary. Some jurisdictions go further. San Antonio requires a bound Smoke Control Report, separate from the plans, prepared by a licensed PE with smoke control experience, including an event matrix, fan calculations, minimum and maximum pressure differences with and without stack effect, and coordination of sprinkler and alarm zones.
3. Size the pressure and airflow
The IBC sets a minimum of 0.05 inches of water gauge across a smoke barrier in a sprinklered building for zoned systems. For exit stairs, the commonly used window is 0.10 to 0.35 inches of water column with doors closed, and Fairfax County's guidelines require it at maximum stack effect and wind conditions.
The upper limit is a door problem, not a fan problem. NFPA's smoke control guidance caps the pressure force so that door opening force does not exceed 30 pounds-force. As a rule of thumb, a 0.35 inch water column pressure produces roughly 21 pounds of force on a standard seven-foot door before you add the closer, which is how an apparently fine pressure can fail a door test.
For exhaust systems, the IBC requires smoke to be kept at least six feet above the evacuation path, and limits air velocity to 200 feet per minute where it could reach the fire plume.

4. Design the stair and its supply
Things that decide whether a stair holds pressure:
- Supply fan location and intake protection so smoke cannot be drawn in.
- Single-injection versus multiple-injection supply on tall stairs, where one point at the bottom can leave upper floors under-pressurized.
- Barometric or modulating relief so pressure does not spike when doors open and close.
- Leakage paths: elevator hoistway doors, shaft walls, door undercuts.
- Power. The system must run on normal and standby power. Fairfax County requires full performance within 60 seconds of a power disruption, citing NFPA 70 Article 701.12.
Where it goes wrong: pressure that works on the commissioning day with two doors open and fails on a windy day with the roof door cracked. Design for the extremes, not for an average day.
5. Design the controls and the fire alarm interface
The IBC requires the control unit to be UL 864 listed as smoke control equipment. Verification includes positive confirmation of actuation, manual override and confirmation that power is present downstream of all disconnects. A firefighter's smoke control panel with ON-AUTO-OFF control over each fan and damper is required in the fire command center of high-rise buildings, and elsewhere next to the fire alarm control panel. Dedicated systems self-test at intervals not exceeding seven days according to the SYNC construction standard, and the California Building Code requires a weekly preprogrammed test.
Where it goes wrong: ordinary building automation controls on shared HVAC equipment. That is the classic rejection at inspection. The boundary between the smoke control controls and the fire alarm system also tends to be assigned to nobody. Name an owner for every point on the event matrix before bid.
6. Document, file and plan the test
AHJs want the design, the construction and the acceptance testing viewed as one package. Write the test procedure while you design the system, not after the fans are installed.
Atrium smoke control
Atriums are a smoke management problem, not a containment one. NFPA 101 Section 8.6.7, as explained in an NFPA article, calls for an engineering analysis that confirms the smoke layer stays at least 6 feet above the highest walking surface for 1.5 times the calculated egress time or 20 minutes, whichever is greater. Where smoke control is required it follows NFPA 92.
NFPA 92 lists six design approaches for large volumes:
| Approach | What it does |
|---|---|
| Natural smoke filling | Lets smoke fill an unoccupied volume or reservoir |
| Mechanical exhaust, hold height | Keeps the smoke layer at a set height |
| Mechanical exhaust, slow descent | Delays the layer coming down |
| Gravity venting, hold height | Uses roof vents to keep the interface up |
| Gravity venting, slow descent | Uses vents to delay descent |
| Opposed airflow | Prevents smoke moving between spaces |
Exhaust needs makeup air. NFPA 92 places the supply below the smoke layer interface, keeps mechanical makeup air below the exhaust mass flow, and holds velocity to 200 feet per minute near the plume unless analysis supports more. Makeup air also cannot push door opening force past the limit, so atrium exhaust and stair pressurization have to be designed together when the atrium opens to an exit.
Inputs that drive the answer: atrium height and floor area, fire size, whether the space is sprinklered, how many levels open into it, and the egress time of the occupants on those levels. These are architectural decisions first, which is why the architect and the mechanical engineer should be sharing a model early.
Smoke control testing and what passes
Testing is not a courtesy. Under IBC Section 909.18.8 and the special inspection provisions, smoke control systems get a special inspection by an agency with fire protection and mechanical engineering expertise, certified as an air balancer. Testing happens twice: during duct installation (leakage, device locations) and at completion (pressure differences, airflows, detection and controls). The report lists each device with its design and measured values, is signed, sealed and dated by the responsible registered design professional, goes to the fire code official, and a copy stays at the building. Fairfax County adds that the system must be inspected and tested before the certificate of occupancy is issued.
Stair pressurization testing
The pass criteria are tested together at every floor:
- Pressure difference across the stair door within 0.10 to 0.35 inches of water column, all stair doors closed.
- Door force within egress limits: 15 pounds to release the latch, 30 pounds to set the door in motion, 15 pounds to swing it fully open (the 2024 IBC adds 28 inch-pounds for turning hardware).
A floor that passes one and fails the other has failed. The usual field fixes are relief damper adjustment, fan speed control tuning, door closer adjustment and sealing leakage, which is why a pre-test walk by the design team before the official inspection saves a day of retesting.
Records you keep
Bellevue, Washington's fire department guidelines list what must stay current in the fire control room for the life of the building:
- Approved control diagrams and plans showing every device.
- A unique address for each device.
- A detailed event matrix.
- Fan curves, maintenance logs and quarterly testing logs.
- The approved design report and the final special inspection report.
The 2025 California Building Code adds device tags dated to the last successful test and a record of who did it. Treat these as the minimum and ask your AHJ what it wants.
Why owners and architects bring this to one engineering team
Smoke control fails at seams: a stair door that the architect specified with heavy hardware, a fan the installer substituted, a waterflow signal nobody mapped to the event matrix. Each trade can do its own piece correctly and the system still fails inspection. The cheapest place to find that is on paper.
A single MEP/FP team can check the stair pressure targets against the door hardware, the sprinkler zones against the event matrix and the power design against the sequence, then carry the package through the permit. That is the thesis of this article: the reader who gets the drawings coordinated before filing avoids the retests, resubmittals and certificate-of-occupancy delays that come from handing the pieces to separate consultants.
Where Bazini Engineering fits
Bazini Engineering, P.C. has provided MEP/FP design and consulting since 2010, with mechanical, plumbing and fire protection disciplines all in-house and licensure in New York and Florida. For smoke control projects, the relevant work sits across our mechanical engineering and fire suppression engineering services, and our permit team handles filings and coordination with the NYC Department of Buildings and FDNY.

If you own or manage an existing building, our building owner services cover mechanical troubleshooting and evaluations, equipment condition and capital planning, boiler and HVAC plant upgrades, and permitting and agency filings. To start a project conversation, see our full list of services or the Bazini Engineering home page.
Our perspective
We treat smoke control as a coordination problem first and a calculation problem second. The math is well documented. What sinks projects is that the stair, the fan, the damper, the alarm point and the permit set were each handled by someone who never saw the others.
Our mechanical, plumbing and fire protection engineers work in the same firm, so a question like "does this door hardware survive the pressure we need?" or "which waterflow device starts this sequence?" gets answered by a senior engineer, not passed through an account manager.
Our advice to owners and architects: bring the engineer in at schematic design, agree the design criteria and the controls ownership in writing, and write the test procedure before the first fan is ordered. Our deep knowledge of NYC codes and agency procedures means that, for New York projects, the filing path is part of the design conversation from day one.
Joseph
FAQ
What are the main types of smoke control systems?
NFPA 92 divides them into smoke containment systems and smoke management systems. Containment covers stair, elevator, vestibule, refuge area and zoned pressurization. Management covers mechanical exhaust and natural or gravity venting for large spaces such as atriums.
What pressure does a pressurized stairwell need?
A commonly applied window is 0.10 to 0.35 inches of water column with all stair doors closed, while keeping door opening force within egress limits. Your jurisdiction's adopted code and AHJ guidance set the exact numbers, so confirm them before design.
Who is allowed to test a smoke control system?
The IBC treats it as a special inspection. It must be done by an agency with fire protection and mechanical engineering expertise that is certified as an air balancer. The responsible registered design professional signs and seals the report.
Can standard building automation controls run smoke control?
Not on their own. Control units for smoke control must be UL 864 listed as smoke control equipment, and shared HVAC controls that lack that listing are a common cause of inspection rejection.
Sources
This article draws on the model codes and standards named in the text (IBC Section 909, NFPA 92, NFPA 101), municipal smoke control guidelines and professional engineering publications. Bazini Engineering service pages referenced: