A medical gas project in New York City needs approval from two agencies, not one. The Department of Buildings (DOB) approves the piping work through a plumbing filing and inspections. The Fire Department (FDNY) regulates the gas itself, through permits and Certificates of Fitness for the people who supervise it. A licensed professional engineer or registered architect files the DOB paperwork, and a Licensed Master Plumber does the work. Teams that treat these as separate tracks from day one avoid most of the delays. This guide walks through each track for owners, property managers, architects and installers.

Baziniengineering
Get Support for NYC Project Approvals
Bazini Engineering offers MEP/FP design, permit expediting support, and coordination with local agencies for projects navigating NYC approvals.
Visit

TL;DR

  • DOB issues plumbing permits only to a Licensed Master Plumber (LMP) or Licensed Master Fire Suppression Contractor (LFSC). The owner hires a New York State-licensed PE, a Registered Architect (RA) or a DOB-licensed plumber to file, and filings go through DOB NOW: Build.
  • FDNY separately requires a permit above set gas quantities. Oxidizing gas such as oxygen triggers it at 504 SCF of compressed gas, or 10 gallons of cryogenic liquid indoors.
  • A G-71 Certificate of Fitness holder must supervise piped medical gas, and one must be on duty 24 hours a day in facilities that use medical gases.
  • Design follows NFPA 99 under the NYC Plumbing Code, with inspections at underground, roughing, test and finish stages, then sign-off and a Letter of Completion.
  • Inspections are at the owner's cost, so budget for them with the engineering scope.

Table of Contents

Two agencies, two approvals

The split is easy to miss because both agencies touch the same room.

DOB is about construction. Under the NYC Plumbing Code 2022, an owner or authorized agent who intends to install, alter, repair, remove, convert or replace a regulated gas, mechanical or plumbing system must first apply for construction document approval and obtain the required permit before work starts. Medical gas piping sits inside that framework. The code was amended by Local Law 77 of 2023, effective June 10, 2023.

FDNY is about the gas and the people responsible for it. Its Fire Code requires a permit to store, handle or use compressed gases above set quantities, and it requires a Certificate of Fitness holder to supervise piped medical gas systems.

A DOB permit does not give you an FDNY permit, and the reverse is also true. A project can have clean plumbing approvals and still stall at turnover because no qualified person has been designated to supervise the system.

Two agencies, two approvals

What counts as medical gas work

The FDNY G-71 materials list the piped non-flammable medical gases covered: oxygen, nitrogen, nitrous oxide, carbon dioxide and medical air, among others. The NYC Fire Code requires the whole system to comply with NFPA 99, the national standard for health care facility gas and vacuum systems. That covers containers, distribution piping, supply manifolds, connections, pressure regulators, relief devices, valves, and monitoring and alarm systems.

In practice, the work that triggers a filing includes:

  • New piped oxygen, medical air, vacuum or nitrous oxide in a clinic, dental suite, surgical center, hospital floor or lab
  • Extending or altering existing medical gas piping during a renovation
  • Replacing manifolds, cylinder storage or bulk cryogenic equipment
  • Adding or relocating alarm panels and zone valves

If you are unsure whether a minor change counts, treat it as a filing question for your engineer before the plumber mobilizes. Local Law 142 of 2025 amends the Administrative Code on the scope of gas piping inspections and ordinary plumbing work, so the line between what needs a filing and what does not is one to confirm against the current DOB rules, not assume.

Who can file, and who can touch the pipe

This is where owners and architects most often get tripped up.

DOB issues plumbing and fire suppression permits only to a Licensed Master Plumber or a Licensed Master Fire Suppression Contractor. Only those licensees, or employees working under their supervision, may work on the piping systems. DOB frames this around public safety: improper gas work can cause fire or explosion, and cross-connected piping can contaminate drinking water.

The filing is a separate role. Before plumbing work begins, the owner must hire a New York State-licensed Professional Engineer, a Registered Architect, or a DOB-licensed plumber to file for the proper permits. Plumbing job filings and permit requests are submitted in DOB NOW: Build, and the owner must approve each filing.

So the project team looks like this:

RoleResponsibility
Owner or authorized agentHires the filing professional, approves filings in DOB NOW, pays for required inspections, maintains the system afterward
PE or RAPrepares drawings and the filing, can submit results-only plumbing certifications, and handles the final inspection for their filings
Licensed Master PlumberHolds the permit, performs or supervises the piping work, runs the tests with the inspector
G-71 Certificate of Fitness holderSupervises handling and use of the medical gas system for FDNY

For plumbers and HVAC or boiler installers who are new to medical gas, note that mechanical rooms and storage rooms are part of the picture, which we cover below.

FDNY permit thresholds

FDNY's G-71 study materials set the quantities that require a permit. Below these amounts, a permit is not triggered, but the DOB side of the project still applies.

Gas typeCompressed gas (permit above)Cryogenic liquid, indoors / outdoors (permit above)
Oxidizing (oxygen)504 SCF10 gallons / 50 gallons
Nonflammable, non-oxidizing3,000 SCF60 gallons / 100 gallons
Carbon dioxide4,500 SCFNot separately stated in the FDNY materials we reviewed

SCF means standard cubic feet, a measure of gas volume at standard conditions. A single large cylinder can hold a few hundred SCF of oxygen, so a suite with a modest manifold can cross 504 SCF faster than owners expect. Add up everything stored on the premises, not just what is connected to the piping.

Certificates of Fitness

FDNY ties the permit to supervision. The G-71 materials state that handling and use of compressed gases in medical gas systems, in quantities requiring a permit, must be under the personal supervision of a G-71 holder. Storage needs general G-71 supervision. Installing and maintaining cryogenic containers and systems must be under the personal supervision of a G-79 holder. FDNY's G-71 page adds that a G-71 holder must be on duty 24 hours a day in all facilities that use medical gases.

That 24-hour requirement is an operations question as much as a permitting one. Owners of small facilities should plan who will hold the certificate and how coverage works before the system is energized, because the certificate is what lets the permit function in daily operation.

Existing installations

FDNY's materials explain that installations approved on or after July 1, 2008 must fully comply with the 2008 Fire Code. Older approved installations need only meet the requirements in effect when they were installed. If an existing installation was never permitted, the owner must give FDNY records, such as the New York State General Municipal Law 209-u inventory forms, that establish the need for the stored quantities. Buying a building or taking a lease with legacy medical gas? Ask for those records early.

From filing to sign-off: the DOB process

Here is the sequence for the plumbing side, with where each step usually goes wrong.

  1. Scope and design. The engineer defines the gas types, outlet counts, zone valve locations, source equipment and alarm layout, and designs to NFPA 99 as the NYC Plumbing Code requires. Chapter 12 of the code governs nonflammable medical and nonmedical gas systems, with portable systems, cylinder storage and vacuum exhaust terminations following the NYC Mechanical Code. Where it goes wrong: drawings that treat the gas source room as an afterthought, which brings objections on ventilation and storage.
  2. Filing in DOB NOW: Build. The PE, RA or plumber submits the job filing, and the owner approves it. DOB reviews and approves plumbing applications before permits issue. Where it goes wrong: owners who do not approve the filing promptly, or who hire a filer who is not licensed in the right category.
  3. Permit to the licensed plumber. Permits go to the LMP or LFSC, not to the owner or the engineer.
  4. Installation with staged inspections. DOB NOW: Inspections lists the medical gas inspection types: MG-PL-UndergroundTest, MG-PL-Roughing, MG-PL-Test and MG-PL-Finish. Results-only plumbing certifications may be submitted by a Master Plumber, Fire Suppression Contractor, RA or PE.
  5. Testing. Under Section 108.4 of the Plumbing Code, tests follow Section 312, are made by the permit holder, and are witnessed by the department. All apparatus, material and labor come from the permit holder. Failed work must be corrected and resubmitted for reinspection. Where it goes wrong: testing equipment not on site, or a test scheduled before the system is ready.
  6. Sign-off. DOB's plumbing guide lists "Medical gas install cert: LETTER-MED" as a work type sign-off document. When the project is complete, PEs and RAs need a final inspection, while LMPs need all inspections and tests done plus final plumbing sign-off, scheduled in DOB NOW: Inspections.
  7. Letter of Completion. After sign-off, the applicant can request a Letter of Completion in DOB NOW: Build.

If the building also has gas service for other uses, note that Gas Authorization Requests are a separate submission. They are made by a licensed plumber, the owner or a delegate in DOB NOW: Inspections after at least one passing Gas Finish Inspection.

The room matters as much as the pipe

HVAC and boiler contractors are often pulled in on this part. The NYC Mechanical Code, Section 502.9.1, sets ventilation rules for compressed medical gas storage. A room holding permit-quantity medical gases that has no exterior wall must be exhausted through a duct to the exterior in a 1-hour-rated shaft enclosure, at a minimum of 1 cfm per square foot. Gas cabinets must connect to exhaust with an average face velocity of at least 200 fpm, and no less than 150 fpm at any point.

Medical gas room exhaust and cabinet airflow criteria

Those numbers affect where the gas room can go on the floor plan, how big the shaft is, and what the mechanical engineer has to carry in the drawings. Deciding the location after the plumbing layout is fixed is a classic source of redesign. A coordinated mechanical and plumbing design avoids it.

Codes that govern today

NYC's construction codes were brought up to date with the 2015 editions of the international codes by Local Law 126 of 2021, effective November 7, 2022. The 2022 NYC Plumbing Code is the current plumbing reference, and the Fire Code's Chapter 53 covers compressed gases. DOB also lists Local Law 142 of 2025 on its local laws page, which touches gas piping inspection scope, ordinary plumbing work and the plumbing and fire suppression piping contractor license board. Rules shift, so confirm the version and any new local law on the DOB site when you start design.

Costs and records to check before you start

Published DOB fee schedules and filing costs change, so confirm them at filing. What does not change is who pays for inspections. The Plumbing Code makes all inspections the sole cost and expense of the owner. It also lets approved agencies or special inspectors perform progress inspections on the owner's behalf, unless the DOB commissioner directs the department to do them for public safety reasons.

Before mobilizing, a short records check saves weeks:

  • Certificate of Occupancy and prior filings for the space, to see what medical gas work was previously approved
  • FDNY permit status and any existing Certificate of Fitness holders on staff
  • Gas inventory and quantities compared with the thresholds in the table above
  • Licenses of the plumber and the filing professional, active and in the right category
  • Owner approval path in DOB NOW: Build, so someone with authority can approve promptly

After turnover, maintenance responsibility falls on the owner or the owner's designated agent under Section 102.3.1 of the Plumbing Code, and the DOB commissioner may require any plumbing system to be inspected for compliance.

What each reader should do next

Building owners and managers: hire the filing professional first, before the plumber bids. Confirm who will hold the G-71 certificate, and plan the 24-hour coverage.

Architects: coordinate the gas source room location and exhaust path with the mechanical engineer early, because it drives shaft and room sizing.

Plumbers and mechanical installers: your permit and your tests are the DOB critical path. Schedule the underground, roughing, test and finish inspections around the actual construction sequence, and have test equipment ready.

How we help

We are a licensed engineering firm in New York and Florida, with all MEP and fire protection disciplines in-house, so the gas piping, the exhaust, and the fire protection around the gas room are designed together. We handle NYC permit filing and coordinate with the NYC Department of Buildings and FDNY, and our plumbing engineering covers domestic water, gas, sanitary and storm layouts. Building owners can see how we work on our building owner services page.

Baziniengineering

If you have a medical gas project in New York City, Long Island or Westchester, start with a conversation with a senior engineer about scope and filing path through our MEP engineering services.

Our perspective

Medical gas jobs rarely fail because the pipe was wrong. They fail because the filing, the gas room, the FDNY side and the plumber's inspection schedule were handled by four different people who did not talk until turnover.

That is why we keep mechanical, plumbing and fire protection under one roof and put clients in direct contact with senior engineers, not account managers. When the person who designs the exhaust shaft also knows the DOB NOW filing path and the FDNY expectations, decisions get made once.

Our advice to owners: settle the filing professional, the gas room location and the Certificate of Fitness plan in the first weeks. Everything downstream gets cheaper.

Joseph

FAQ

Does every medical gas project need an FDNY permit?

No. FDNY requires a permit when stored or used quantities exceed its thresholds, such as 504 SCF of compressed oxygen or 10 gallons of cryogenic liquid oxygen indoors. Piped systems still need a Certificate of Fitness holder for supervision, and the DOB plumbing filing applies regardless of the FDNY permit.

Can the owner or a general contractor pull the permit?

No. DOB issues plumbing permits only to a Licensed Master Plumber or a Licensed Master Fire Suppression Contractor. The owner hires a New York State-licensed PE, RA or DOB-licensed plumber to file, and approves that filing in DOB NOW: Build.

Which inspections apply to medical gas piping?

DOB NOW: Inspections lists medical gas inspections for the underground test, roughing, test and finish stages. After final sign-off, including the medical gas install certification document, the applicant can request a Letter of Completion.

Who pays for the inspections?

The owner. The NYC Plumbing Code makes inspections the owner's cost and expense, and it allows approved agencies or special inspectors to perform progress inspections on the owner's behalf in most cases.

Who needs a G-71 Certificate of Fitness?

The person supervising piped non-flammable medical gas systems. FDNY states a G-71 holder must be on duty 24 hours a day in facilities that use medical gases, so most facilities need more than one qualified person.